Dispatch’s Amethyst battery energy storage system (BESS) in Dordrecht is a 45 MW / 90 MWh stand-alone battery designed to provide flexibility to the Dutch electricity system. Developed by Dispatch and equipped with battery technology from Fluence, Amethyst is one of the Netherlands’ largest stand-alone battery storage projects.
Following grid connection, commissioning and extensive testing, Amethyst entered commercial operation in October 2026. The battery can now actively participate in energy markets, helping balance electricity supply and demand while supporting the integration of renewable energy.
Spectral provides the advanced Battery Energy Management System (EMS) through its STELLAR platform. Acting as the central integration and control layer, STELLAR connects the battery, electrical infrastructure, grid operators and external energy market systems into a single operational environment. The platform enables real-time monitoring, automated alerting, reliable execution of control instructions and continuous management of technical and grid-related constraints.
As renewable energy capacity grows, large-scale battery storage is becoming increasingly important for maintaining a flexible and reliable electricity system. Batteries can store electricity when supply exceeds demand and release it when needed, while providing valuable services to energy markets and the grid.
However, operating a 45 MW / 90 MWh battery requires much more than the physical storage infrastructure. Large-scale BESS projects involve a complex ecosystem of interconnected IT and OT systems, each serving different operational purposes and often supplied by different technology providers.
For Dispatch, the challenge was to establish a central energy management and control platform capable of integrating the Fluence battery system with its supporting electrical infrastructure, including medium- and low-voltage distribution equipment, switchgear, transformers, site metering and auxiliary systems. Reliable monitoring and automated alerting across these systems are essential to ensuring safe and efficient operations.
At the same time, Amethyst needed to respond to control instructions from Eneco, responsible for optimizing the battery’s participation in wholesale and ancillary services markets, while continuously respecting the battery’s technical limitations and the grid connection’s operational constraints.
Grid congestion management adds another layer of complexity. As the Dutch electricity grid becomes increasingly congested, battery projects must be capable of operating within dynamically changing grid capacity limits and supporting grid operators in maintaining network stability. For Amethyst, this required integrating multiple congestion management mechanisms, including real-time intervention capabilities for distribution system operator Stedin and the automated management of contractual grid capacity restrictions.
As Amethyst represents Dispatch’s first large-scale battery project, scalability was another important consideration, with the ambition to support future battery assets through a common Virtual Power Plant (VPP) infrastructure.
Spectral implemented its STELLAR platform as the central operational backbone of Amethyst, connecting the various on-site and external systems into an integrated energy management and control solution.
Comprehensive site integration and operational monitoring
Acting as the spider in the web, STELLAR connects the Fluence BESS with the site’s wider electrical infrastructure, including medium- and low-voltage distribution equipment, switchgear, transformers, site metering, HVAC and other Balance of Plant systems.
By collecting and processing real-time operational data, STELLAR provides comprehensive site-wide visibility through its cloud-based user interface. The platform continuously monitors critical parameters, detects abnormal conditions and automatically routes alerts and notifications to the responsible parties, enabling timely intervention and efficient operational coordination.
Energy market integration and advanced battery control
STELLAR integrates with Eneco’s optimization infrastructure, enabling Amethyst to participate in Day-Ahead and Intraday trading, as well as ancillary services including FCR and aFRR.
While Eneco provides market optimization and dispatch instructions, the STELLAR Power Plant Controller (PPC) ensures their reliable execution through the Fluence battery control system, continuously accounting for technical limitations and grid constraints. STELLAR also provides Eneco with real-time operational feedback and asset availability information to support its optimization activities.
Advanced grid congestion management through Stedin and GOPACS
A distinctive feature of Amethyst is the integration of two complementary congestion management mechanisms.
STELLAR is one of the few solutions in the Netherlands certified to support the Real Time Interface (RTI). Its direct connection to Stedin’s RTI endpoint enables the distribution system operator to intervene in battery operations in real time when needed to safeguard regional grid stability.
In parallel, STELLAR integrates with GOPACS, the Dutch grid operators’ congestion management platform, to automatically retrieve contractual grid capacity limits. These limits can vary over time and are typically established a day in advance.
The STELLAR PPC continuously incorporates these dynamic limits into its control logic, ensuring that Eneco’s dispatch instructions are executed without exceeding the permitted grid capacity. Together, these mechanisms combine proactive congestion management with real-time grid operator intervention, enabling flexible battery operation within an increasingly constrained electricity network.
Reliable implementation and ongoing operations
The implementation combines on-site control infrastructure with cloud-based monitoring and operational services. Spectral coordinated the technical integration with project partners and conducted commissioning and end-to-end testing, including communication, control and failover functionality.
Following commissioning, Spectral continues to provide operational support, including active monitoring, incident response, maintenance and software updates.
In October 2026, Amethyst successfully entered commercial operation following completion of grid connection, commissioning and extensive testing.
With 45 MW of power capacity and 90 MWh of energy storage, the battery can deliver up to two hours of electricity at its rated output. Through its integration with Eneco’s optimization infrastructure, Amethyst can participate in multiple electricity markets and provide valuable flexibility to the Dutch energy system.
STELLAR provides the technological backbone that makes these operations possible, bringing together battery control, site-wide infrastructure monitoring, automated alerting, energy market connectivity and advanced grid congestion management in a single integrated platform.
The implementation also demonstrates how large-scale battery storage can operate effectively within increasingly constrained electricity networks. Through its integrations with Stedin’s Real Time Interface and GOPACS, STELLAR enables Amethyst to participate in energy markets while respecting dynamic grid capacity limits and supporting the operational needs of the local grid operator.
For Dispatch, the project establishes a scalable energy management foundation that can be extended to future battery projects and integrated into a broader VPP infrastructure.
Amethyst represents an important milestone for Dispatch and its partners, including Fluence, Equans, Eneco, Stedin, Ventolines and Spectral, who have contributed to bringing the project from development and construction into commercial operation.